Owner:

Basin Electric Power Cooperative

Boldt Role:

Construction Manager

Key Points:

The preconstruction phase requires a constructability review of all design documents and drawings. The goal of this phase is to identify opportunities to improve efficiency and minimize potential problems in the field that could impact cost and schedule.

Basin Electric Power Cooperative

Deer Creek Station

Brookings County, SD

Boldt's scope for the project included complete management and construction of the energy center. Included are all civil, structural, mechanical, piping, electrical and controls work associated with the installation of a one-on-one combined cycled plant.

The major equipment components that were erected by Boldt consist of one GE Class F Combustion Turbine, one Nooter/Eriksen HRSG, one Alstom Steam Turbine and one SPX Air Cooled Condenser. The combustion turbine and steam turbine are located in an enclosed structure with an attached administration building. The water treatment building is separate.

Boldt provided civil/structural, boilermaker, and millwright skills as self-performed services.